IT Exam,IT Certification,braindump,original questions, question pool,document, braindump, test questions, test question, dumps, test answers, cert24.com, preparation, pdf, certification questions, answers Certification, certification test, practice test, exam dumps, certification training, answers real questions
CA0-001 Certified Associate in Project Management our products come with a 100% guarantee of success. We hold this claim because of the highly dedicated and expert team that we have and because of our past performance.
Exam dumps, software Testing engine Testcenter PMI CA0-001 cert24
QUESTION NO: 1
The work breakdown structure is ________.
A. Used to break down the project into manageable pieces
B. Set and does not change throughout the project
C. Needed as part of the project charter
D. [Needed as part of the project scope statement
Answer: A
Explanation:
Work Breakdown Structure (WBS): A deliverable-oriented grouping of project elements which organizes and defines the total scope of the project. It sub divide the major tasks to minor details.
QUESTION NO: 2
If a project with a SPI of 1.8, what you tell?
A. The project is running ahead of the schedule
B. The project is running behind of the schedule
C. Resources assigned to the project cost 1.8 units
D. None
Answer: A
Explanation:
The SPI equals the earned value divided by the planned value. SPI = EV/PV A schedule
performance index of 1 or greater suggests that the project is ahead of schedule.
QUESTION NO: 3
You are managing a project that will implement a new MARKETING software package. You have assigned the resources and want to keep the IT manager in the loop by informing him or her of your decisions. Which type of organizational structure are you working in?
A. Pi’ojectized
B. Strong Matrix
C. Weak Matrix
D. Functional
Answer: B
Explanation:
Projectized Organization: Any organizational structure in which the project manager has full authority to assign priorities and to direct the work of individuals assigned to the project. Strong Matrix: The project manager is assigned full time and has a full time support staff. Project manager has the preeminent position of authority. Weak Matrix: Power reset with Functional Manager.
Functional: In this organization Project Manager has least power and all management is taken care by functional manager like marketing engineer, sales engineer.