In view of the increasingly competitive society and in order to meet the needs of the consumers.I want to recommend that our productC_TSCM42_64 in the it-exams.com.are suitable for you,because Our experts come from different parts of the Industry and are most experienced and qualified to have the opportunity to write the exam practice test for us.
Practice test eases the preparation of exam and validate knowledge. Practice Test contains multiple learning modes, easy and robust user interface, Self-Assessment reports, Detailed Test Result Reports, simulates real exam environment and many more features. our products are developed in sucha way in which all the candidates can prepare exam anywhere, anytime. Printable PDF helps candidates to have the hardcopy with them and study anytime, anywhere. Installable application helps them in practicing the questions while they are in office or at home. Online Tool helps everyone who just have an internet connection with him/her on any device and he/she can study. By providing all these product
exam practice test provides comprehensive coverage of C_TSCM42_64 Exam Objectives while keeping it all still simple enough for you to understand it easily. When you order the it-exams C_TSCM42_64 Practice Exam Test Questions, we shall offer you free update on time for one year. Superior and also Benefit to the C_TSCM42_64 test questions, 100% Assure to feed An individuals C_TSCM42_64 test Review, Downloadable, Interactive C_TSCM42_64 Screening sites, Proved Answers Reviewed through Specialist, Pull and also Lose questions seeing that familiar with the very C_TSCM42_64 study materials,Process Examination Issues along with shows. Your C_TSCM42_64 Practice Exam Test Questions tend to be endorsed through the 100% Money-back guarantee.
QUESTION NO: 1
In production order processing, for which of the following objects can you enter a confirmation? (Choose three.)
A. Work Center
B. Individual Capacity
C. Order
D. Operation / Suboperation
E. Trigger Point
Answer: B,C,D
QUESTION NO: 2
Which one of the following scheduling types cannot be assigned as default to an order type (production order)?
A. Midpoint
B. Forward
C. Only capacity requirements
D. Backward
Answer: A
QUESTION NO:3
In your enterprise, a planning strategy is used in SAP ECC that enables joint planning of all MRP scheduled assemblies for a finished product to trigger procurement of these assemblies. It is important to ensure that the finished product is only produced when there is a customer order present. When a customer order is received, production of the finished product should be triggered in the form of make-to-order planning and production.
Which planning strategy covers this scenario?
A. Planning with make-to-stock (strategy 10)
B. Planning at the assembly level (strategy 70)
C. Planning with final assembly (strategy 40)
D. Planning without final assembly (strategy 50)
Answer: D
QUESTION NO: 4
An enterprise based in the USA produces an end product that is used with the unit of measure “pound” (LB). The material is now to be marketed in the EU. A prerequisite for this is that the material can be sold with the unit kilogram (KG).
Which of the following solutions does SAP ECC offer?
A. In the basic data customizing, you create a unit of measure group that converts pounds to kilograms. You then assign this to the material master on basic data view 1.
B. You create a new material with a reference to the original material and assign the metric unit of measure to the new material master.
C. In the material master, you create a conversion factor for converting pounds to kilograms on basic data view 1.
D. There is no need to take any action. There is a general conversion in the central customizing of units of measurements, so that automatic conversion of pounds to kilograms takes place.
Answer: D
QUESTION NO:5
Which of the following functions are available in the SAP ECC system for leveling overloads in individual work centers with the capacity planning tools? (Choose three.)
A. Midpoint scheduling
B. Batch size optimization
C. Lot size optimization
D. Setup time reduction
E. Finite capacity scheduling
Answer: A,D,E