C_TSCM42_66
QUESTION NO: 1
You want to use the function “Read PP master data” in the production order.
However, while calling the function you receive an error message.
What could be the reason?
A. The material availability check has been performed.
B. Goods movements have been posted.
C. The production order has been released.
D. Order papers have been printed.
Answer: B
QUESTION NO: 2
Which objects can affect the calculation of capacity requirements for an operation? (Choose three)
A. Standard values (routing)
B. In-house production time (material master)
C. Transport time (routing)
D. Formulas (work center)
E. Operation control key (routing)
Answer: A,D,E
QUESTION NO: 3
In the Customizing for requirements planning, a project team notices that the alternatives P1, P2, P3 and P4 are also delivered as standard in addition to MRP type PD. The number in each of these alternatives represents a firming type.
What does a firming type define? (Choose two)
A. Handling existing procurement proposals outside the planning time fence.
B. Handling existing procurement proposals within a planning time fence.
C. Handling new requirements within the planning time fence.
D. Handling new procurement proposals that need to be created due to new requirements within the planning time fence.
Answer: B,D
QUESTION NO: 4
Which of the following scheduling types can only be used in capacity planning?
A. Midpoint
B. Forward
C. Only capacity requirements
D. Backward
Answer: A
QUESTION NO: 5
Which types of objects can be changed with Engineering Change Management (ECM)? (Choose three)
A. Task list
B. Work center
C. Production version
D. Bill of material
E. Material master
Answer: A,D,E
C_TSCM42_65
QUESTION NO: 1
What features related to process orders can be used to fulfill Good Manufacturing Practices (GMP) requirements? (Choose three)
A. Availability check
B. Digital signature
C. Resource selection
D. Electronic batch record
E. Approved master recipes
Answer: B,D,E
QUESTION NO: 2
Which of the following statements about consumption are correct? (Choose two)
A. Consumption takes place on the material level between the planned independent requirements and the planned orders.
B. Consumption parameters (consumption mode and consumption interval) can be set in the material master or in the MRP group.
C. Consumption is restructured with the planning run.
D. Consumption can take place between order reservations and planned independent
requirements, depending on the strategy.
Answer: B,D
QUESTION NO: 3
Where can you define the valid receivers for production order costs?
A. In the valuation variant
B. In the production scheduling profile
C. In the settlement profile
D. In the costing variant
Answer: C
QUESTION NO: 4
When analyzing the SAP ECC order report for a planned order for a finished product, you discover that one of the assemblies will not be available in time for the scheduled final assembly because of automatic forward scheduling.
Which planning procedure do you use to create a feasible production plan from a requirements planning perspective?
A. Interactive single-item planning for the delayed assembly
B. Multi-level single-item planning with the “simulation mode” option
C. Total planning online
D. Multi-level single-item planning with the “display material list” option
Answer: B