EX0-002 Practice Test Questions

EX0-002 Practice Test Questions

  • Code:EX0-002
  • Click Here: more information
  • Exam Demo:
  • QUESTION NO: 1
    When considering risks, which describes an opportunity in a project?
    A. An uncertain event that could have a negative impact on objectives
    B. An uncertain event that could have a favourable impact on objectives
    C. An event that has occurred resulting in a negative impact on objectives
    D. An event that has occurred resulting in a favourable impact on objectives
    Answer: B
    QUESTION NO: 2
    Which of the following statements about lines of authority and reporting are true?
    1, The Project Manager has day-to-day control for a management stage within the limits laid,
    2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager down by the Project Board.
    A. Only 1 is true
    B. Only 2 is true
    C. Both 1 and 2 are true
    D. Neither 1 or 2 are true
    Answer: C
    QUESTION NO: 3
    Which may be funded from a risk budget?
    A. Corrections due to off-specifications
    B. Impact analysis of requests for change
    C. Implementation of a fallback plan
    D. Preparation of the Risk Management Strategy
    Answer: C
    QUESTION NO: 4
    What is the first task of product-based planning?
    A. Produce the Initiation Stage Plan
    B. Write the Project Product Description
    C. Identify dependencies
    D. Create the product breakdown structure
    Answer: B
    QUESTION NO: 5
    How many tasks does the product-based planning technique describe?
    A. One
    B. Two
    C. Three
    D. Four
    Answer: D

Comments are closed.